No Gyrtle Tire Soup!

Hey, hey, hey – we have launch.  As with everything it took a little longer than anticipated to get Gyrtle off of her jacks.  And, I had problems with two tires – one on Gyrtle and one on my truck.  In order to take care of things my wonderful assistant – Mike Ring – and I had to set up the compressor to fill the tires.  This entailed going to Lowe’s to get “fixin’s”.

Once we had the tools we needed we noticed that the air wasn’t really filling the tire – and then we heard a faint hissing from the valve.  In a way it was good to find out right away what the problem was – a bad valve.  So then we needed to get the tire off and put on the spare.  I thank God for strong young men – specifically for Mike.  Even he tore up his hand applying the needed pressure to loosen the nuts on the tire.

The tire on my truck wouldn’t fill completely so I’ll go today to where I can get more pressure.  But that tire is holding enough pressure to drive Gyrtle to a station.  Or maybe Allfleet will be able to fill ‘er up for me.

So, the truck was attached to Gyrtle with no problems.  We saw the flat and the low tire and took care of those.  We moved all the materials that had been stored under the trailer and then we completed removing all the other jack stands and supports until my home was settled onto terra firma via her own wheels and the truck!  You will see from the photos that the springs held up and the tires didn’t squish.  Yaaay!

Of course, I’ll still be adding a number of thousands of pounds with my batteries, generator, propane tanks, solar panels and interior finishing, and of course my personal belongings.  But, I feel all is well.

Yesterday was a different sort of 4th of July here in Colorado Springs.  After the tremendous Waldo Canyon fire and it’s devastation things were pretty quiet – no fireworks anywhere, no barbecues allowed.  There was a big concert at the World Arena with the symphony, the cowboys from the Flying W Ranch (which was burned out) and a number of other local musicians to raise money for the displaced people.  I must give a shout out to the amazingly virtuosic yodeler – I’ve never heard anything like that before.

The great work of the firefighters is hailed over and over.  Many homes were saved by their good work and the fire now is 80% contained (or more).  It was kind of nice to have quiet acknowledgement of freedom, community, the importance of paying attention to and caring for the earth and lots of gratitude.

TTFN

How Heavy Is That Thing!?

“How heavy is that thing?” is the disturbing question I’ve been asked numerous times over the last couple of months.   Usually it is followed by one of the two addendums:  “As soon as you remove the jacks your tires are going to explode.” or “As soon as you remove the jacks the tires are going to sink into the wheel wells and you ain’t goin’ nowhere!”

Well, tomorrow we will see just what it means that my trailer is rated at 14,000 pounds and the tires are rated to carry that load as well.  I know the framing of my house is around 7,000 pounds and my question to all of these doomsday prophets is, “What the heck does it mean to have a trailer that is rated at 14K pounds if it doesn’t mean it’s rated at 14K pounds?”  The same goes for the tires.  Geez, what do we have all these regulations and standards for?  I have actually had someone tell me that just because the rating says such-and-such, it doesn’t mean that it will perform that way.

So tomorrow – actually later today – I’m taking my trailer off of its jacks and taking it to be weighed and then to get the radiant flooring and water heater installed.  Wish me well and stay tuned for the triumphant report that the sky didn’t fall.  TTFN (Ta-ta for now)

Progress Slows Down – Frustrations Abound

Hi Folks,

At this point we got word that our father’s house (where my brother and I were living), which had been on the market a fairly brief time, had a second buyer who wanted to settle by the 15th of May – which was only three weeks away.  I had arranged for my carpenter’s wife, Chris – a really good friend of mine, to come from Oklahoma.  Originally she was going to cook for us and help out where she could.  But when we got the final definite word that the settlement would be on the 15th all plans changed.

Clearly my house would not be finished by the end of May and clearly Chris was going to be needed to help finish packing up the house and getting out.  We had one week when she arrived.  While we were packing up, I had to get the siding (which we had brought to the house from my site to coat with oil/stain/preservative) painted and backt o the site so Dan could put it up.  He was working mainly by himself now because I had to be at the house.  So his progress was slowed down too.  At least I found out that I really had been needed.

In spite of all – which included ordering special stainless steel, ribbed siding nails from Indiana – we did manage to get almost all of the siding up before Chris and Dan left at the end of seven weeks and two half-days of work.  Dan also got everything prepped so that the roof could be put on.

We ran out of the special nails before completing the siding and the new order didn’t arrive until they had left.  The roof had also been delayed for some reason and finally arrived on May 17th instead of April 30th.  I found a roofer pretty easily to install the roof – and it went on days earlier than projected! – except for the last two pieces – because we ran out.  So it’s another two weeks to wait for those pieces to come in.

Dan also finished the porch which is just lovely.  I really enjoy sitting out there on my rocker, feeling the breeze and looking at Pikes Peak.  I really couldn’t have picked a better site to build on than this for so many reasons.

My electrician also came by for a day and we started wiring.  It was a lot more time consuming than I would have thought to get really specific about where I wanted lights and switches and plugs and all the little other things that needed power when you have a house that is a hybrid between a house and an RV.  In fact, I’m still working on choosing lights and fans.  I’m not real happy with what I’m finding on the DC sites.  In the end I think my brother Mark will make DC lights from AC lights I find that I like and we’ll put LED bulbs in them.

This brings us up-to-date with weeks 6-7 and 8.

Roof, Tyvek and a Loft

A lot happened this week too.  I screwed in tons of screws on the roof.  To be fair, Dan did half the roof and I did the other half. We got most of the Tyvek up.  It got too windy to be up on the tall ladders so we had to stop.  We also got the Bitch-i-thane (properly known as Ice and Water Shield) in place on the roof and the front of the trailer.  We also have a floor on the sleeping loft.  Grandkids now have a place to sleep.  And Windows!  Not quite dried-in, but getting pretty close.

End of week five.

Finishing Walls/Roof Begins

Hi Folks,

This week my space begins to take on overhead dimension also.  It was interesting that as we put more parts together my home no longer felt so awkwardly huge and my fears of it being of odd proportion started to go away.  It began to feel just right and just as I had imagined it.

We did go through a bit of a reexamination of things as we approached the roof and ordering roofing material.  The walls were higher than we originally intended and we had to lower the pitch of the roof a bit to make sure I wouldn’t be over 13.5′ tall from the ground.  This gave us some concern about the required pitch to satisfy the requirements of the metal roof.  It also changed the needed length of the panels for the roof (to shorter, fortunately), but they had already been ordered, so that’s the way it was.

And so was the end of week four.

The Beginning of Walls

Oh, these first weeks were exciting as (big) things started happening.  Once we knew we could proceed – that’s just what we did.  Every week we thought we would get more done than we did, but still, there was progress.  The weather was generally great – not too hot, not too cold.  A bit too windy. At times we had real concerns of things blowing apart before we could get them stabilized.

While we (Dan mainly) were framing I had to spend many mornings at Home Depot and elsewhere ordering materials and picking up supplies – or taking things back.  I had wanted to design one section of the framing all by myself but the timing never worked out for that.  I cut many of the boards though and did a ton of screwing in plywood between floor, walls and roof.

Actually, a lot has happened

Hi Folks,

Oh my gosh, a lot has happened since I wrote last – it’s hard to figure out where to begin.  Can’t decide if I just go ahead and post a picture of where things stand right now or make you wait and go back to week two.

I think I’ll do a little of both – show you one picture of how things are now and then go back and fill in the details by weeks.  All along the way there have been things that didn’t go as planned.  Researching materials has been and remains time consuming.  Some items are delayed in arriving.  Some come and are the wrong thing.  People get sick.  Items get charged to me twice – blah, blah, blah.

I’m sure that anyone who has built anything, or taken on any big project knows that these delays are to be expected.  In fact, even though it tries my patience, I know that it has been necessary to working out the right order of things and making the correct choices to have these delays.  I just don’t like it much.

Here’s Gyrtle right now, in all her semi-completed, complete dried-in state.

You will see that I have all my siding (almost) completely stained (almost).  Also, I have my complete roof on (almost – if you look close).  Oh well, one day these things will be completely complete.

So, back to week two.  There are two nests of magpies in the trees behind my house.  This one seemed to be claiming the territory of this strange object coming up so close to its home.

The end of the first week was tough because we didn’t know how to proceed.  I’m going to have radiant floor heat and we really didn’t know what materials to use and how to install them.  If the radiant floor was to go under the subfloor we couldn’t proceed.  But a few trips to ABC Plumbing and consulting with Kurt helped us come to the conclusion that we could go ahead and put the subfloor down with insulation in it and much later in the process we could put the radiant floor panels down.  So we were finally ready to proceed!

In these pictures you’ll see the progression from having just the aluminum which goes under the whole of the structure for protection from water, to putting in the floor joists, having the shiny aluminum that covers both sides of my insulation installed and finally the subfloor is on.  Most of the pictures are of me enjoying walking on my floor the first time and seeing that my idea of the space and what I want in it will actually work.  The only floor missing is my bedroom which will be up on the gooseneck.

Oh Happy Day!

Building Begins!

Hi Folks,

The day finally came – Dan, my carpenter, arrived.  He got here a day later than expected but that turned out to be perfect.  If he’d arrived on Tuesday he would have arrived in the midst of a snowstorm on an incredibly cold, grey day and would have found me in my pajamas, barely able to get out of bed.

When he arrived on Wednesday the sun was shining, the snow melting, and we got started with showing him around the town, getting him set up in his digs and introducing him to Gyrtle.  Thursday we met with Scott to talk over details and then went to move the trailer to it’s exact building spot and get it leveled.  Then we went hunting for southern yellow pine to fill in the flatbed to provide support for the aluminum that will protect the belly of my home from water and invading rodents.

There was no southern yellow pine to be found anywhere so we finally decided on a substitute – douglas fir, I think – which had to be primed.  This happened on Friday.  We also spent most of Friday locating suppliers for various plumbing supplies and getting the order of lumber and other building materials lined up for delivery on Saturday with Home Depot – or maybe that was Thursday.

First thing Saturday morning the truck arrived with the building supplies.  Unfortunately all of the insulation we got was wrong so that will have to go back on Monday.  Saturday we also put those white boards on the trailer.  I actually sawed some of them.  Then we started rolling out the aluminum and siliconing it down.  It was a very cold day and lots of wind so I was glad that nothing blew away – or blew us over.

I find I vascillate between thinking “Wow, this is really cool” and “OMG, how is this actually going to get done?”  There is so much to do, so much to buy, so many details to be worked out.  I did have a moment when I could feel my Dad looking down from the great beyond, enjoying that I was building my own home.

Whistle while you work!

Here are My Drawings of Gyrtle

Hi Folks,

Here are some drawings of how I want my space to be set up.  Because these aren’t photos you need to click on each link to see the drawing – I couldn’t make a true gallery.  These are the kinds of drawings I like to look at and dream about.  Scott, my A&E (architect and Engineer), has detailed drawings that builders like to look at, of course.  I’ll ask him if it’s ok to put those up here too.

Today when I went to buy my self-tapping metals screws at ACE Hardware they had animal walking sticks – sticks with carvings of animals at the end.  They had one of a Turtle!  So I bought it.  I also bought the aluminum for the protection of the bottom of my home.

Sunday it was 82 degrees here.  Today, cold and windy and tonight it is snowing.  I don’t mind if we have snow tonight as long as it melts before Dan gets here and we don’t have to put off starting the building because of a blizzard!

Basic Drawing on Scott’s Template

Some Views of My Home

More Views of Gyrtle

It’s a long and winding road…

Visiting the Trailer at its New Home

Hi Folks,

We got the trailer to its new home in Colorado Springs on Dec. 8th and had a meeting at the trailer to get a closeup look-see and measurements on the 9th.  This is where Gyrtle will be built.  Well, not the exact spot.  We’ll move the trailer to the exact spot in the lot and level it probably on April 3rd – and get started.

I still haven’t ordered the materials though.  I keep having too many questions and I’m just not confident yet that I will buy the correct items.   As far as the wood is concerned, at least, Home Depot has it available immediately.  So I may just wait til Dan, my carpenter, gets here and we can go together and pick it out and make sure it’s right.  I will have to get the aluminum to protect the bottom of my home though.  I promise, I’ll do that tomorrow.  Think I’ll put in another call to my A&E too.

Happy Trails,